Estimate the quantity of soil to be excavated from the borrow pit​

Respuesta :

lola2487
lola2487 lola2487
  • 04-08-2019

Answer

1056

Explanation:

for example

A soil is to be excavated from a borrow pit which has a density of 1.75g/cc and water content of 12%. The G is 2.7 the soil is compacted to that water content of 18% and dry density of 1.65g/cc. for 1000 m3 of soil used in fill estimate

Quantity of soil to be excavated from pit in m3

Answer Link

Otras preguntas

simplify the expression:37!/37option:A. 39!B. 36!C. 37!D. 38!​
I need help! No links, please!
What are the 4 main factors of production? Give two examples for each one.
9. The sum of two consecutive even numbers is 242. What are the two even numbers?
the levels of nourishment in a food chain are called
Can someone tell me the answer to this please???
help me please!! i wasn’t at school the day so help meee
How does financial resource influence the development of a nation? write in two sentences.​
What is Joshua's speed if he won a 30 meter race in 40 seconds
In ancient civilizations, dances were performed as rituals for the government. true or false?