if 28 men can complete a work in 16 days wiil 8 men take to complete that work is it a.14 b.48 c.56 d.128

Respuesta :

Brissy516 Brissy516
  • 12-09-2020

Answer:

56

Step-by-step explanation:

Answer Link

Otras preguntas

The slow rate of a particular chemical reaction might be attributed to which of the following? a) a low activation energy b) a high activa
Yo insisto que ella ______________ a las doce.
The system of equations above is graphed below. Find the solution to the system.
What is the value of x if 3x-6=21
Which is true of the of the United Nation in 1945? The United States chose not to be a part of the United Nations. The United Nations wanted to help spread capi
In the ______________ process of DNA replication, each of the single strands becomes a double strand as an enzyme connects the appropriate complementary base to
To think critically about a reading​ passage, the first thing you should do is A. make a list of things to be critical about. B. do a word count. C. form a conc
What can you conclude about the crystals in Image A relative to the crystals in Image B? (2 points) The crystals in Image A had less room to grow than the cryst
Square EFGH is drawn on a coordinate plane. Diagonal FH is on the line y − 3 = negative one third(x + 9). What is the slope of the diagonal GE? A. -1/3 B. 1/3
if a word is capitalized in the middle of a properly wriiten sentence chances are the word is