  • Mathematics
contestada

Mr. Kumar is getting his house renovated. 1/5 th of the work has been completed in 2 months. How much time will it take for the entire work to be completed?

Respuesta :

liam2747
liam2747 liam2747
  • 02-05-2021

Answer:

10 months

Step-by-step explanation:

If it takes 2 months to do 1/5th, it will take 4 months to do 2/5, 6 months to do 3/5, 8 months to do 4/5, and 10 months to do 5/5 or in other words the whole thing.

Answer Link

Otras preguntas

The area of a rectangle is 21 in2. The length of the rectangle is 6 in. What is the width of the rectangle?
how can you define a mixed number and the first one two answer gets 24 pts
Cody is designing a pattern for a wood floor the length of the pieces of wood are 1 1/2 inches 1 13/16 inches and 2 1/8 inches what is the length of the fifth p
what is epazote used for
human-envioronmental interaction takes place in rural,not urban,areas true or false
All of the following were surplus crops of the South except: rice wheat indigo
What happens when introducing a gene into a new organism
Dory and Nemo go to Taco Bell for lunch. Dory orders three soft tacos and three double deckers for $11.25. Nemo pays $10.00 for four soft tacos and two Double D
If a person living in one state sues a person living in another state for a sum exceeding $75,000, they can choose to originate the case in the state or federal
settlers came from___ to the americas seeking mainly religious freedoms in the 1600s