A work system has five stations that have process times of 5, 9, 4, 9, and 8. What is the bottleneck time

Respuesta :

andromache andromache
  • 04-06-2021

Answer:

9

Explanation:

Given that

There is five stations who have the process time of 5,9,4,9 and 8

We need to find out the bottleneck time

so, as we know that the bottleneck is the duration of the activity who have longer time

So as per the given situation the 9 has the longest duration activity time

So, the same is to be considered

Answer Link

Otras preguntas

Solve using quadratic formula x squared -2x-8=0
What is the GCF for 24, 48m
What are some characteristics of medieval music?
What circumstances prevented England from expanding its territories as quickly as other European nations
what is 5 times something equals 120
the krazy kite company is planning to produce kites.the company has rented space for its manufacturing operation at $6,000 per month. each kite requires $37 wor
here is a food chain in a meadow. Use this food chain to answer this question. Grass, Field Mouse, Corn Snake, Hawk Which is the producer in the meadow? A. fiel
A Rectangle Measures 11Cm By 30 Cm. What is its area?
Three times the square of a number if five less than sixteen times the number. What is the number?
The diameter of a quarter it's about 2.4 cm what is the ratio of the radius of the quarter to the diameter of the quarter