Activity A B C D E F G H Time 5 3 7 6 7 3 10 8 a. Identify the critical path. b. How much time will be needed to complete this project

Respuesta :

aristeus aristeus
  • 06-07-2021

Answer:

Critical path = A-D-F-H

Duration = 22

Explanation:

Given:

Activity A B C D E F G H

Time 5 3 7 6 7 3 10 8

The objective is to identify the critical path and to find the time needed to complete this project

Solution:

The possible paths are as follows,

A-C-H = 5+7+8 =20

A-D-F-H = 5+6+3+8 =22

A-D-G = 5+6+10 = 21

B-E-G = 3+7+10 = 20

B-E-F-H = 3+7+3+8 = 21

a)

Critical is the path with the longest duration

Critical path =A-D-F-H

The duration is 22

b)

The duration to complete the project is as follows,

Duration = Length of critical path = 22

Answer Link

Otras preguntas

Tom has twice as many marbles as Luke. Together they have 39 marbles. How many marbles does Tom have?
Crops produce the greatest amount of waste, mainly from plant parts not harvested as food. Why are most people less concerned about crop waste than other types
The variables x and y are inversely proportional, and y=2 when x=3. What is the value of y when x=9?
Why do geographers study human systems and human environment relationships?
Why do many different types of proteins exist even though there are a limited number of amino acids
How much is this shaded Please help
Each year Earth moves once around —
what natural resources were available to Meso-America?
What does W = too Please help
A sphere is dilated by a scale factor of 1.04 to create a new sphere. How does the volume of the new sphere compare with the volume of the original sphere?