32 workers can complete a work in 30 days working 6 hours per day. How many days are required to complete the
same work by 16 workers working 8 hours per day?

Respuesta :

Tasyha
Tasyha Tasyha
  • 03-09-2021

Answer:

45 days

Step-by-step explanation:

[tex]32 \times 30 \times 6 \div (16 \times 8) [/tex]

[tex]5760 \div 128[/tex]

[tex]\boxed{\green{ = 45}}[/tex]

Answer Link

Otras preguntas

log4 (x+4) = 1 ? I assume you distribute log base of four to (x+4). But I don't know how to go about it, please help!!
.0162 as a mixed number
The composer __________ began in the classical vein and later became known for his romantic style.
plz help yall guys do plz to 7
there are 100 elephants if u ad 2 more and add another 2 more how much will u get
This is a famous painting about the birth of? Jupiter Juno Minerva Venus This structure is an example of a roman column, tomb, temple, bath
Match the terms to their correct examples or descriptions. 1. body language 2. tone and body language 3. resolving conflict 4. good way to handle conflict
can anyone help me with history I will voter?
How do I find dy/dx of the equation 4x^3-3xy^2+y^3=28 at the point (3,4)?
please help! i don't understand